Previous site access roundabout Scheme

IPaD assisted developer group Elan Homes with a S73 application to amend the details and requirements for off-site highways junction improvements as appended to an earlier outline planning application for their site.

The requirement for IPaD’s input came about once it was made clear at the delivery stage of the development that the initially proposed and accepted highways work flagged up unforeseen constraints to their delivery and that in engagement with IPaD, advice was recommended to the client that indicated better alternative schemes could be delivered that offered reduced level of constraint and which could be considered acceptable in highways design terms.

IPaD supported this process by undertaking new detailed design drawings and supporting information to support the justification for the change in schemes being proposed.

The S73 application was met with resistance from the Local Parish Council local resident groups and despite a positive recommendation by the highway’s authority, the application was rejected at planning committee and subsequently went to appeal.

To support the appeal process IPaD was the named expert witness group and was charged with the production of a written statement of case and written rebuttals to the listed objections as raised by the planning authority.

IPaD successfully rebutted all counter objections, and the appeal was subsequently upheld by the Planning Inspector. The scheme has now moved towards the full delivery stage and IPaD continues our role as principal designer and is working alongside the highways authority in bringing forward a S276 agreement for delivery of the highways works.

New T-Junction Scheme

Related Previous Work

Residential Scheme – Acton

IPaD assisted Clearview Homes in the delivery of a new residential led mixed-use development located off the A40 in Acton, Ealing originally consisting of up to 80 residential apartments and a 100+ bed hotel development. The brownfield site, formerly a petrol station was originally acquired by Transport for London (TfL) and was intended to be ... Read more

Hay End Lane – Fradley, Lichfield

Working on behalf of JT Leavesley, IPaD assisted with the formulation of a transport evidence base to support an outline planning application for a 300+ residential development with ancillary mixed use on a greenfield site located to the north of Lichfield on the edge of Fradley Village. A comprehensive package of information was provided in ... Read more

Apedale Road – Newcastle Under Lyme

IPaD was commissioned by Gleeson Homes Ltd to assist in the delivery of a 300+ home residential development located on a former colliery site off Apedale Road in Newcastle Under Lyme. The site had long standing consent as part of an earlier 2013 planning application which required the previous applicants to provide £549,000 in off-site ... Read more